23rd Ave construction update: Major detour changes begin November 30, Cherry St work this Saturday


Major construction detour changes begin November 30
On Monday, November 30, crews will extend the northbound closure of 23rd Ave from E Cherry St to E Union St (Zone B) as construction progresses north. This means northbound 23rd Ave will be closed from S Jackson St to E Union St with detours to Martin Luther King Jr Way. Southbound traffic will be maintained in Zones A and B. 23rd Ave will remain open to traffic in both directions from E Union St to E John St. Read the latest construction notice for more information, including a map of the upcoming detour configuration.
Schedule update
Crews have made good progress rebuilding 23rd Ave since construction began in June, and the project is on schedule for completion in early 2017. However, the timing and phasing of the northbound detour has changed from original plans and now includes some overlap between Zone A and B. This overlap is needed to keep the overall project on schedule as a result of construction challenges encountered in Zone A with the planned locations for the new trolley poles.
Here is the latest schedule by zone:
Zone A (S Jackson St to E Cherry St)
  • Full northbound detour began June 2015 and is expected through spring 2016
Zone B (E Cherry St to E Union St)
  • Full northbound detour to begin November 30 and continue through summer 2016
Zone C (E Union St to E John St)
  • Early utility work is underway now through January 2016
  • Full northbound detour is anticipated to begin in spring or summer 2016 and extend through early 2017
We know construction can be difficult, and we appreciate your patience as we construct important safety and mobility improvements. For more information about the schedule update, read the new Frequently Asked Questions document on the website.
Intersection closure at E Cherry St November 21
Crews plan to close the E Cherry St and 23rd Ave intersection this Saturday from 7 AM to 10 PM to continue storm drainage and electrical work, though this work is weather dependent. View the detour routes for the intersection closure here. Don’t forget you can enter local access areas to get to businesses and residences near the intersection.
Mark your calendars for our December drop-in session
Tuesday, December 8, 4:30-6:30 PM
Garfield Community Center Multipurpose Room
2323 E Cherry Street, Seattle, WA 98122
Other construction activities
  • Crews will conduct night work near the intersection of E Pike St and 23rd Ave on November 20 – 21 in order to make temporary water main connections. Neighbors should expect construction activities throughout the night and into Saturday morning. This work will coincide with temporary water service interruptions.
  • On November 12, crews closed Garfield High School's southern driveway on 23rd Ave for up to two weeks in order to demolish and pave a nearby section of 23rd Ave. During this closure, school buses are using a temporary load zone on E Alder St between 23rd and 25th avenues. Expect increased bus traffic and travel delays long E Alder St during school pick-up and drop-off times.
  • Crews continue replacing the water main in Zone C. During this work, drivers can travel both north and south on 23rd Ave, though travel is reduced to one lane in each direction.
  • Crews continue to demolish and repave sidewalks from S Jackson St to E Yesler Way on the east and west sides of 23rd Ave. Please use caution and pay attention to sidewalk closures and pedestrian detours.

For more information

Visit: www.seattle.gov/transportation/23rd_Ave.htm
Email: 23rdAveCorridor@seattle.gov
Call the 24-hour project hotline: 206-727-8857